Instructions and supervision of the assessment of level crossing risks

Implemented

Rail R

Accident

18.7.2019

2019-S47

Suosituksen perustelu

There was no process for the handling of the risk assessment required by the authority for the track project, and there were no instructions on the matter. The identified risks did not lead to measures being taken.

Recommendation

The Finnish Transport and Communications Agency shall define an approval process for the risk assessment of level crossings and supervise that the corrective measures are taken.

Toimenpide-ehdotukset

There was no process for the handling of the risk assessment required by the authority for the track project, and there were no instructions on the matter. The identified risks did not lead to measures being taken.